The success story of eab Projektmanagement GmbH
2011
294 MW
- eab celebrates 20 Years Renewable Energy
- Heliotec Energiesysteme GmbH, founded in 1991, adopts the technical and commercial management of wind energy turbines in Germany under the name of eab Windservice GmbH
- Market entry in the direct sale of wind energy
2010
281 MW
- eab has commissioned 201 wind energy turbines and 281 MW with a total investment of approx. 410, 000,000 €
- Setting up of eab windservice Sp. z o.o. for technical and commercial management of wind energy turbines in Poland
2009
276 MW
- In Poland we have developed a project volume of 20 MW ready for building
- We opened our office in Hanoi and start to develop large-scale projects in Vietnam.
2008
267 MW
- eab implements its first wind energy project in Poland: Inowrocław with 32 MW
- With the setting up of eab Projektmanagement GmbH we restructure the company. Acting as a super-ordinate company eab Projektmanagement GmbH takes over strategic decisions and thus simplifies company-wide actions.
2007
212 MW
- On the ridge of the Erzgebirge (Ore Mountains), south of Freiberg, we erected currently the biggest wind farm of the Czech Republic with 42 MW, so far our largest project abroad.
- Altogether we have implemented a project volume of 167 wind energy turbines with a total rated power of 212 MW and an investment volume of 290, 000, 000 €.
2006
165 MW
- eab erects currently the biggest wind farm of Central Germany: Alsleben with 36 wind energy turbines and a total rated power of 54 MW.
- Market entry in Poland: Opening of the eab office in Bydgoszcz.
2004
107 MW
- We exceed the 100-MW-limit and our biggest project so far goes on line: wind farm Holleben with 17 GE 1.5 sl-turbines and 25.5 MW.
- eab is involved in the implementation of its first wind farm abroad, on the Isle of Pag in Croatia.
- Expansion of our activities into Hungary: participation in Schnell-Invest Kft.
- eab starts with the implementation of the first and at the same time biggest tracking solar park in Eastern Germany.
2003
75 MW
- We erect the first wind energy turbines in Saxony with a hub height of 100 m: wind farm Zodel with 8 GE 1.5sl.
- eab achieves the 100 Million Euro-limit of total investments.
2002
53 MW
- eab establishes its Italian subsidiary, Italian Wind Power s.r.l. and starts planning activities in Sardinia.
- Enlargement of our business activities to technical and commercial management of wind energy turbines
2000
40 MW
- We have put into operation 56 wind energy turbines with approx. 40 MW.
- eab starts business activities abroad with the development of large-scale projects in the Czech Republic and Brazil.
1995
10 MW
- Setting-up of eab Projektbau GmbH for the development and turnkey erection of wind farms in Germany, the abbreviation eab stands for the German word “Energie-Anlagen-Bau” (i.e. erection of power generators).
- eab implements four wind energy projects.
1994
3 MW
- Implementation of our first wind farm: Clausnitz.
- Starting with the preparation of wind potential and energy yield expert reports for own projects and for the planning of third parties.
1993
0.3 MW
- Planning and erection of our first and at that time most powerful wind energy turbine of the type Südwind N3127 (270 kW) in Dittmannsdorf near Freiberg.
1991
- Setting-up of Heliotec Energiesysteme GmbH and of Heliotec Ingenieurbüro (engineering office) in Freiberg in order to develop concepts for the use of renewable energies.
- First wind measurements for wind potential and energy yield studies.
- As pioneer of wind energy co-founder Dr. Rainer Sack accompanied the development of the company from the beginning and is today the Managing Director of eab Projektmanagement GmbH.
All MW-data are accumulated values of installed wind energy capacity